The outline of the programme of works is as follows:

•  Internal soft strip demolition started in Autumn 2017 allowing the main structural demolition to proceed from January 2018 and this will be complete to the Gloucester tower area in July 2018.

•  Works to the substructure have commenced from May 2018 and will continue until Spring 2019.

•  The superstructure and envelope of the buildings will be ongoing between Summer 2018 and Spring 2020.

•  Internal fit out of the buildings will commence in early 2019.

•  This will allow the phased completion and occupation of the buildings to commence from Summer 2020 with the final homes being available in Spring/Summer 2021.




The outline of the programme of works is as follows:

•  Internal soft strip demolition started in Autumn 2017 allowing the main structural demolition to proceed from January 2018 and this will be complete to the Gloucester tower area in July 2018.

•  Works to the substructure have commenced from May 2018 and will continue until Spring 2019.

•  The superstructure and envelope of the buildings will be ongoing between Summer 2018 and Spring 2020.

•  Internal fit out of the buildings will commence in early 2019.

•  This will allow the phased completion and occupation of the buildings to commence from Summer 2020 with the final homes being available in Spring/Summer 2021.